пока там мелкие доделки еще пару месяцев. ограничение 100 км.ч
К концу лета 2018го откроют последний строящийся кусок S8
общий список открытий в 2018м году:
S7: west of Drweca bridge – east of Drweca bridge 1km (June 2015 to January 2018)
S5: Ostroda-South (S7) – Ostroda-West 8.7km (June 2015 to March 2018) [2nd c/w]
S12: Pulawy-Deblinska – Pulawy-Azoty 1.3km (April 2016 to April 2018) [2nd c/w]
S12: Pulawy-Azoty – Kurow-West (S17) 11.1km (April 2016 to April 2018)
S3: Nowa Sol-South – Gaworzyce 16.4km (August 2015 to June 2018)
S3: Gaworzyce – Polkowice-North 16.9km (July 2015 to June 2018)
S3: Lubin-North – Lubin-South 11.3km (September 2015 to June 2018)
S3: Lubin-South – Legnica-South (A4) 22.6km (July 2015 to June 2018)
S5: Leszno-South – Rydzyna 9.5km (May 2016 to July 2018)
S8: Wyszkow-North – Poreba 13.0km (March 2016 to July 2018)
S8: Poreba – Ostrow Mazowiecka-South 16.1km (March 2016 to July 2018)
S8: Ostrow Mazowiecka-North – Prosienica 9.4km (March 2016 to August 2018)
S11: Kepno-North – Kepno-Krazkowy (S8) 4.1km (November 2016 to August 2018)
S3: Jawor-East – Bolkow 16.1km (April 2016 to September 2018)
S5: Lipno – Leszno-South 19.2km (May 2016 to September 2018)
S7: Zulawy-West – west of Nowy Dwor Gdanski 18.9km (October 2015 to October 2018)
S7: south of Nowy Dwor Gdanski – Elblag-South 20.0km (October 2015 to October 2018)
S7: Radom-North – Radom-South 25.2km (December 2015 to October 2018)
S8: Siestrzen – Paszkow 11.6km (August 2016 to October 2018)
S11: Bielice (S6) – Koszalin-West 2.0km (March 2016 to July 2018)
S3: Legnica-South (A4) – Jawor-East 19.7km (June 2016 to October 2018)
Возможны задержки:
S3: south of Zielona Gora-South – Niedoradz 8.0km (April 2015 to May 2018) [2nd c/w]
S3: south of Zielona Gora-North – north of Zielona Gora-South 2.8km (October 2015 to May 2018) [2nd c/w]
S3: Niedoradz – Nowa Sol-South 17.3km (March 2016 to August 2018) [2nd c/w]
A1: Czestochowa-Blachownia – Czestochowa-South 4.7km (July 2016 to November 2018)
A1: Wozniki – Pyrzowice (S1) 15.2km (September 2015 to November 2018)
S3: Polkowice-North – Lubin-North 14.4km (October 2015 to June 2018)
S10: Walcz-West – Witankowo 17.8km (November 2015 to June 2018)
S7: Kielce-South – Jedrzejow-North 21.5km (June 2015 to Mid 2018)
S5: Poznan-West (A2) – Mosina 16.0km (August 2015 to 2018)
S6: Bielice (S11) – Sianow-East 19.3km (March 2016 to July 2018)
S5: west of Bydgoszcz-Blonie (S10) – Szubin-North 9.7km (August 2017 to October 2018)
S7: Skomielna Biala – Zabornia (DK47) 5.2km (April 2016 to July 2018)
S7: Lubien – Naprawa 7.6km (July 2015 to October 2018)